Sustainable construction process

Although a project attempting to meet LEED requirements for VOC limits in paints, coatings and adhesives has called for specific content limits in all applicable project specifications, what is an easily overlooked set of products that may jeopardize compliance with VOC limits in the project?



Answer: Touch-ups are often made with incorrect products because the amounts are small, but the presence on the jobsite of non-compliant products can jeopardize credits concerned with low-emitting materials.
are-review.blogspot.com

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD