Conditions of the contract

What type of "conditions of the contract" can be used on multiple projects, for the same client or another?
A. special conditions, B. supplementary conditions
C. general conditions, D. standard conditions


Answer is B. supplementary conditions customize the general conditions for different clients, local laws and government regulations.
are-review.blogspot.com

Comments

Try These Too!

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP

Mold

Mold is one of the potential contributors to poor indoor air quality and it requires 1. moisture, 2. a nutrient and 3. a particular temperature range. What temperature range supports its growth and which requirement is key to controlling its growth? Answer 40deg - 100deg F (4deg - 38deg C). Thus moisture control is the only way to prevent mold in buildings. ARE 4.0 exam study: BS