Conditions of the contract

What type of "conditions of the contract" can be used on multiple projects, for the same client or another?
A. special conditions, B. supplementary conditions
C. general conditions, D. standard conditions


Answer is B. supplementary conditions customize the general conditions for different clients, local laws and government regulations.
are-review.blogspot.com

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Footing cross-section

When the thickness of a foundation wall = 6", the cross-sectional proportions in this image are appropriate for which of the following: A. a footing supported on clay soil B. light frame construction supporting one floor and one roof C. allowable bearing capacity of foundation soil is low in relation to building loads D. when a continuous footing is required Answer B. light frame construction supporting one floor and one roof (in accordance with Table 1805.4.2) ARE 4.0 exam prep: PPP