Skip to main content

Contractor responsibilities

According to A201 General Conditions of the Contract, which of the following is the contractor NOT obligated to keep at the job site?
A. drawing set, B. specifications, C. bidding documents, D. addenda, E. samples



Answer is C. bidding documents are not required and are not part of the contract documents, unlike bidding package items (A, B, D) which are included in the contract documents.
are-review.blogspot.com

Comments

Try These Too!

Stone shape and usage

Which of the following forms of stone is irregular with a minimum of one good face and is used for ashlar veneers, curbs, sills, and copings? A. Monumental stone B. Rubble stone C. Dimension stone D. Rough stone Answer B. Rubble stone. ARE 4.0 exam prep: BDCS

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°