Match the flame spread and smoke developed index values with the corresponding wall & ceiling finish class:
flame spread 0-25
flame spread 26-75
flame spread 76-200
smoke developed 0-100
smoke developed 0-450
smoke developed >500

Class A =
Class B =
Class C =

AnswerA=flame 0-25, smoke 0-450; B=flame26-75, smoke 0-450; C=flame 76-200, smoke 0-450

ARE 4.0 exam prep: BCDS

Comments

Try These Too!

Space programming

What are two common ways to identify and document physical and functional relationships amongst spaces in the programing phase? Choose 2 A. adjacency diagram B. adjacency matrix C. bubble diagramming D. block-stack diagram Answer A & B The adjacency diagram and adjacency matrix are used in programming stage, while C & D are employed as the initial design effort begins as more physical representations of plan are introduced. ARE 4.0 exam prep: PPP

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Construction type

Fire-resistance rating requirements listed in IBC Table 601 list major building elements based on construction classification. Match these two criteria correctly, choose 2 A. Type IB = roof construction 1 1/2 hrs B. Type IIB = exterior bearing walls 1 hr C. Type IIIA = structural frame 1 hr D. Type VB = floor construction 1 hr E. Type IVHT = exterior bearing walls 2 hr Answer C. and E. are correct. HT = heavy timber. ARE 4.0 exam prep: BDCS Reference tip:  Find the online version of Table 601 in this discussion paper here