Match the flame spread and smoke developed index values with the corresponding wall & ceiling finish class:
flame spread 0-25
flame spread 26-75
flame spread 76-200
smoke developed 0-100
smoke developed 0-450
smoke developed >500

Class A =
Class B =
Class C =

AnswerA=flame 0-25, smoke 0-450; B=flame26-75, smoke 0-450; C=flame 76-200, smoke 0-450

ARE 4.0 exam prep: BCDS

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS