In this Critical Path Method scheduling fragment, what must occur prior to Activity C?
A. Activity A
B. Activity B
C. Both A and B
D. Nothing
AnswerC. Both A and B must precede Activity C (same is true for Activity D).
ARE 4.0 exam prep: PPP
A. Activity A
B. Activity B
C. Both A and B
D. Nothing
AnswerC. Both A and B must precede Activity C (same is true for Activity D).