An architecture firm that is implementing a quality control program during construction documents phase would incorporate which of the following procedures:
A. have individuals outside the project team confirm that documentation comply with in-house quality standards.
B. have individual members of the project design team verify that documentation conforms with in-house quality standards.
C. assess previous projects through total quality management for keys to improvement
D. implement an ISO 9000 audit.

AnswerA. is correct. QC is intended to examine whether QA processes have been performed. TQM refers to a process of continuous improvement. ISO 9000 are quality standards that relate to a quality management system, sometimes necessary for international practice.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.