An architecture firm that is implementing a quality control program during construction documents phase would incorporate which of the following procedures:
A. have individuals outside the project team confirm that documentation comply with in-house quality standards.
B. have individual members of the project design team verify that documentation conforms with in-house quality standards.
C. assess previous projects through total quality management for keys to improvement
D. implement an ISO 9000 audit.

AnswerA. is correct. QC is intended to examine whether QA processes have been performed. TQM refers to a process of continuous improvement. ISO 9000 are quality standards that relate to a quality management system, sometimes necessary for international practice.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

Space programming

What are two common ways to identify and document physical and functional relationships amongst spaces in the programing phase? Choose 2 A. adjacency diagram B. adjacency matrix C. bubble diagramming D. block-stack diagram Answer A & B The adjacency diagram and adjacency matrix are used in programming stage, while C & D are employed as the initial design effort begins as more physical representations of plan are introduced. ARE 4.0 exam prep: PPP

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry