Document conformance

An architecture firm that is implementing a quality control program during construction documents phase would incorporate which of the following procedures:
A. have individuals outside the project team confirm that documentation comply with in-house quality standards.
B. have individual members of the project design team verify that documentation conforms with in-house quality standards.
C. assess previous projects through total quality management for keys to improvement
D. implement an ISO 9000 audit.

AnswerA. is correct. QC is intended to examine whether QA processes have been performed. TQM refers to a process of continuous improvement. ISO 9000 are quality standards that relate to a quality management system, sometimes necessary for international practice.

ARE 4.0 exam prep: PPP

Comments

Try These Too!

Wood stairs

In wood stair construction, what is the difference between a carriage and a stringer?! Answer A carriage is the principle support for the treads and risers, whereas the stringer is the finish member (face) that treads and risers terminate against. ARE 4.0 exam prep: BDCS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS