The following language stipulates a minimum review period for submittals.
4.2.7.1 In no case will the Architect's review period on any submittal be less than ______ days after receipt of the submittal from the Contractor.
In what document is this section found?
AnswerNone. Gen. Conditions of the Contract and the Owner-Architect agreement refer to the contractor's schedule of submittals, but no turn-around limit. This model language would be added to section 4.2.7 of A201. Refer to AIA document A503-2007 for further guidance on contract modifications for A201 and model language.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Deflection: steel or wood

For EITHER steel or wood beams, a question that asks for the allowable deflection limit (maximum) for live loads only requires which of the following equations? A. L/240 B. L/360 C. ∆ = 5wl⁴ / 384EI D. ∆ = 5Wl³ / 384EI Answer B. L/360 or span in inches divided by 360. ARE 4.0 exam prep: SS Note on calculations: From posted discussions on AREforum , memorization of most equations is not advised. However, even when the equation may be available in in-exam reference, selection of the appropriate equation requires correct identification.

Facility parking

A new office complex is being planned, which is required to include 162 parking spaces. In addition to the parking spaces, allow for related driveways and walkways to estimate the area of the parking lot that would satisfy this number of spaces. A. 1.0 acres B. 1.5 acres C. 1.75 acres D. 2.0 acres Answer B. 1.5 acres. Multiply the required parking spaces by 400 sf per car (1 acre = 43,560 sf). If walkways are not required, use 300 sf per car. ARE 4.0 exam prep: SPD