The following language stipulates a minimum review period for submittals.
4.2.7.1 In no case will the Architect's review period on any submittal be less than ______ days after receipt of the submittal from the Contractor.
In what document is this section found?
AnswerNone. Gen. Conditions of the Contract and the Owner-Architect agreement refer to the contractor's schedule of submittals, but no turn-around limit. This model language would be added to section 4.2.7 of A201. Refer to AIA document A503-2007 for further guidance on contract modifications for A201 and model language.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred