The following language stipulates a minimum review period for submittals.
4.2.7.1 In no case will the Architect's review period on any submittal be less than ______ days after receipt of the submittal from the Contractor.
In what document is this section found?
AnswerNone. Gen. Conditions of the Contract and the Owner-Architect agreement refer to the contractor's schedule of submittals, but no turn-around limit. This model language would be added to section 4.2.7 of A201. Refer to AIA document A503-2007 for further guidance on contract modifications for A201 and model language.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD