Submittal review

The following language stipulates a minimum review period for submittals.
4.2.7.1 In no case will the Architect's review period on any submittal be less than ______ days after receipt of the submittal from the Contractor.
In what document is this section found?
AnswerNone. Gen. Conditions of the Contract and the Owner-Architect agreement refer to the contractor's schedule of submittals, but no turn-around limit. This model language would be added to section 4.2.7 of A201. Refer to AIA document A503-2007 for further guidance on contract modifications for A201 and model language.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Space programming

What are two common ways to identify and document physical and functional relationships amongst spaces in the programing phase? Choose 2 A. adjacency diagram B. adjacency matrix C. bubble diagramming D. block-stack diagram Answer A & B The adjacency diagram and adjacency matrix are used in programming stage, while C & D are employed as the initial design effort begins as more physical representations of plan are introduced. ARE 4.0 exam prep: PPP

Overimprovement

While underimprovement describes property that is not being put to its highest and best use (reducing its value), when does overimprovement apply?

Construction type

Fire-resistance rating requirements listed in IBC Table 601 list major building elements based on construction classification. Match these two criteria correctly, choose 2 A. Type IB = roof construction 1 1/2 hrs B. Type IIB = exterior bearing walls 1 hr C. Type IIIA = structural frame 1 hr D. Type VB = floor construction 1 hr E. Type IVHT = exterior bearing walls 2 hr Answer C. and E. are correct. HT = heavy timber. ARE 4.0 exam prep: BDCS Reference tip:  Find the online version of Table 601 in this discussion paper here