Which party is responsible for completing the form AIA G715 Supplemental Attachment for Acord Certificate of Insurance?
1. Owner
2. Architect
3. Contractor

Answer3. Contractor (or rather Contractor's insurance representative.) G715 is attached to the Acord Certificate, which lacks the space to summarize all the coverages required in A201, General conditions.

ARE 4.0 exam prep: CDS

For a current listing of AIA Contract Administration and Project Management Forms see this link to the AIA

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry