AIA G715 - 1991

Which party is responsible for completing the form AIA G715 Supplemental Attachment for Acord Certificate of Insurance?
1. Owner
2. Architect
3. Contractor

Answer3. Contractor (or rather Contractor's insurance representative.) G715 is attached to the Acord Certificate, which lacks the space to summarize all the coverages required in A201, General conditions.

ARE 4.0 exam prep: CDS

For a current listing of AIA Contract Administration and Project Management Forms see this link to the AIA

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred