Why can shortening the scheduled time of construction decrease the contractor's overhead?

AnswerAlthough direct costs may increase as overtime or additional workers are added, the contractor's overhead is decreased by shortening the overall time necessary to carry certain project overhead costs such as insurance, heat/cooling, project office or security.

Comments

Try These Too!

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred

Brick bonds

What distinguishes the English Bond pattern from the Dutch Bond pattern in this image? Answer In the English Bond, stretchers are aligned; In the Dutch (cross), stretchers move by a half each course (not aligned). ARE 4.0 exam prep: BDCS

Collector walks

Walks next to parking areas where vehicles are able to overhang the walk should be a minimum width. What is this minimum in feet? A. 3 feet B. 4 feet C. 5 feet D. 6 feet Answer These walks should be 6 ft (D.) minimum in width. ARE 4.0 exam prep: SPD