Why can shortening the scheduled time of construction decrease the contractor's overhead?

AnswerAlthough direct costs may increase as overtime or additional workers are added, the contractor's overhead is decreased by shortening the overall time necessary to carry certain project overhead costs such as insurance, heat/cooling, project office or security.

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Vapor retarders

In this section, a ceiling assembly separates the attic space above from the room interior below. If the building is located in Lewisville, Texas (hot-humid zone), where is the predicted location of condensation and what is the predicted condition of the gypsum board in this assembly? (Select 2 from the following) A. outside face of vapor retarder B. inside face of vapor retarder C. gypsum board will be wet D. gypsum board will be dry