Why can shortening the scheduled time of construction decrease the contractor's overhead?

AnswerAlthough direct costs may increase as overtime or additional workers are added, the contractor's overhead is decreased by shortening the overall time necessary to carry certain project overhead costs such as insurance, heat/cooling, project office or security.

Comments

Try These Too!

Structural forces

Choose a term that best identifies the type of force shown in this diagram - A. collinear B. concurrent C. nonconcurrent D. noncoplanar

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred