Skip to main content

High slopes

What percentage slope is considered very steep or high and what are these slopes subject to?

AnswerSlopes of 50% or greater are quite high and are prone to erosion, fires and mud slides. These areas should be avoided as building sites.

ARE 4.0 exam prep: SPD

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD

Footing cross-section

When the thickness of a foundation wall = 6", the cross-sectional proportions in this image are appropriate for which of the following: A. a footing supported on clay soil B. light frame construction supporting one floor and one roof C. allowable bearing capacity of foundation soil is low in relation to building loads D. when a continuous footing is required Answer B. light frame construction supporting one floor and one roof (in accordance with Table 1805.4.2) ARE 4.0 exam prep: PPP