Concrete form ties


Unless stainless steel ties are specified, ACI (American Concrete Institute) recommends patching, partially filling or plugging the finished depression / holes left by form ties in the concrete surface. Why?




To prevent corrosion of the tie or staining of the concrete surface.
are-review.blogspot.com

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Clear Floor Area

What is the clear floor area required for this front approach at an accessible water fountain? (yellow dash line) A. 36 x 60 B. 36 x 48 C. 30 x 48 D. 30 x 60 Answer C. 30 x 48. Although set in an alcove, the depth of the recess is not 24 inches or greater, which requires a 36 inch clear width. ARE 4.0 exam prep: SPD

Building setback

Which of the following determines building setback requirements (required minimum distances from property line to building)? A. deed restrictions B. building codes C. bulk plane covenant D. zoning regulations Answer D. zoning regulations ARE 4.0 exam prep: SPD