Architect services

The scope of services to be provided in AIA B101 is described in both Architect's basic services and under additional services. Outline specifications should be included in which of the following?

A. Schematic Design Phase Services
B. Design Development Phase Services
C. Construction Documents Phase Services
D. Additional Services: Fast-track Design Services

AnswerB. Design Development Phase Services. Major systems, materials and expected levels of quality are outlined in the design development phase. Detailed specifications are provided in the construction documents phase.

ARE 4.0 exam prep: CDS

Comments

Try These Too!

Calculate Luminance

A typical 60-watt standard frosted incandescent bulb outputs 890 lumens for an efficacy ratio of about 15 lumens per watt. As an A19, its shape is spherical. What is the its calculated luminance? A. 25,115 cd/in² B. 25.115 cd/ft² C. 25,115 cd/m² D. Indeterminate, missing variable. Answer If 1 candela (cd) = 4 ∏ lumens (lm), 890 x 1cd/4∏ = 71 cd, A19 = 19/8 = 2.375 in or 60mm diameter (= 30mm radius), L = intensity / projected area, 71 cd / ∏ r² = 71/ 3.14 x (.03m)² = 25,115 cd/m² ARE 4.0 exam prep: BS

Characteristics of form

Which example illustrates a regular ordering of elements producing RHYTHM? A B C D Answer Answer is C. A = proportion, B = symmetry, D = balance ARE 4.0 exam prep: PPP

Roof pitch

Which one of the following slopes in this illustration corresponds with an 8:12 pitch roof? A. 45° B. 36.87° C. 33.69° D. 26.57°