Fire door time ratings

An exterior wall with a 2 hour rating requires a door assembly rating (standard door test NFPA 252) of 1 1/2 hours. If the exterior wall rating is increased to 3 hours, what is the required door assembly rating?
A. 1 1/2, B. 2
C. 2 1/2, D. 3



A. 1 1/2 is correct. Only a partition used as a fire wall or fire barrier rated above 2 hours requires a door assembly rating greater than 1 1/2 (3 hour door req'd). An exterior wall would not separate another occupancy from the door opening.
are-review.blogspot.com

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.