Fire door time ratings

An exterior wall with a 2 hour rating requires a door assembly rating (standard door test NFPA 252) of 1 1/2 hours. If the exterior wall rating is increased to 3 hours, what is the required door assembly rating?
A. 1 1/2, B. 2
C. 2 1/2, D. 3



A. 1 1/2 is correct. Only a partition used as a fire wall or fire barrier rated above 2 hours requires a door assembly rating greater than 1 1/2 (3 hour door req'd). An exterior wall would not separate another occupancy from the door opening.
are-review.blogspot.com

Comments

Try These Too!

Curb cuts

In a curb ramp that has either built-up or flared sides, the maximum slope of the incline should not exceed 1:12. What is the maximum slope of the (flared)sides in these types of curb ramps? A. 1:8, B. 1:10, C. 1:12, D. 1:16

Thermal insulation

Which of the following types of thermal insulation can be blown into wall or ceiling cavities with least difficulty, but contains no adhesive properties? I. Cellulose II. Rock wool III. Vermiculite IV. Mineral wool V. Straw VI. Polyicynene Answer I, II and III are loose-fill types of insulation that can be blown. IV comes in batts, V can come in boards or bales, VI is a spray-foam that adheres to the cavity. ARE 4.0 exam prep: BS

Bolted connections

What is the minimum spacing of bolts specified by AISC? and preferred spacing? A. 1 1/4 times the diameter of the bolt; 2 times preferred B. 1 3/4 times the diameter of the bolt; 2 1/4 times preferred C. 2 1/3 times the diameter of the bolt; 2 2/3 times preferred D. 2 2/3 times the diameter of the bolt; 3 times preferred E. 3 times the diameter of the bolt; 3.25 times preferred