Skip to main content

Nonconforming work

A Contractor installs millwork on a project that does not conform to the requirements, but does exceed the quality specified in the Contract Documents. Upon review, the Owner decides to accept the work as installed. Which of the following statements is correct? Choose 2.
A. the Owner may not accept without issuing a construction change directive.
B. the Contractor may increase the Contract Sum by an appropriate and equitable amount.
C. no change in the Contract Sum is required as the Contractor has volunteered the better quality.
D. if the Owner accepts, removal and correction is not required.
E. if the work was discovered after final payment was made, the Contract Sum cannot be adjusted for this discrepancy.


Answers C. and D. are correct. The Contract Sum can only be reduced by acceptance of nonconforming work, which can be effected post final payment if not previously discovered. Refer to A201-2007 article 12, section 12.3.
are-review.blogspot.com

Comments

Try These Too!

Bidding process

If the Owner would like to change the designated bid opening date and time contained in the Instructions to Bidders for the Owner's convenience, what procedure must be used? Answer

Fire evacuation

Which of the following statements best describes why exterior fire escapes are no longer recommended or usually permitted? A. Manufacturing has ceased production of these. B. Rising smoke from lower floors eliminates the safety of using them C. They cannot be securely attached to typical current construction D. They are difficult to maintain Answer B. is the correct answer. Smoke inhalation is as perilous as leaping flames. ARE 4.0 exam prep: BS

Tensegrity

A type of structure whose integrity is derived from the balance between members in tension and in compression is Tensegrity . Compressive components connected by tensile components to other compressive components form a tensegrity structure. What architect-engineer-cosmologist coined this term? Answer