Skip to main content

Nonconforming work

A Contractor installs millwork on a project that does not conform to the requirements, but does exceed the quality specified in the Contract Documents. Upon review, the Owner decides to accept the work as installed. Which of the following statements is correct? Choose 2.
A. the Owner may not accept without issuing a construction change directive.
B. the Contractor may increase the Contract Sum by an appropriate and equitable amount.
C. no change in the Contract Sum is required as the Contractor has volunteered the better quality.
D. if the Owner accepts, removal and correction is not required.
E. if the work was discovered after final payment was made, the Contract Sum cannot be adjusted for this discrepancy.


Answers C. and D. are correct. The Contract Sum can only be reduced by acceptance of nonconforming work, which can be effected post final payment if not previously discovered. Refer to A201-2007 article 12, section 12.3.
are-review.blogspot.com

Comments

Try These Too!

Vertical louvers

On which elevations of a building are vertical louvers generally more effective? Select 2 A. East B. South C. West D. North Answer A. East and C. West (answer applies for northern hemisphere) ARE 4.0 exam prep: SPD

Friction loss

Friction loss or static head in sizing of air ducts is given in this expression of units: A. pounds per square inch B. inches of water per 100 feet C. inches of refrigerant per 100 feet D. inches of water per foot Answer B. inches of water per 100 feet ARE 4.0 exam prep: BS

Joint ventures

Which AIA document series includes agreements for joint ventures? A. A-series B. B-series C. C-series D. D-series E. G-series Answer C. C-series covers architect/consultant documents including joint ventures.