Skip to main content

Nonconforming work

A Contractor installs millwork on a project that does not conform to the requirements, but does exceed the quality specified in the Contract Documents. Upon review, the Owner decides to accept the work as installed. Which of the following statements is correct? Choose 2.
A. the Owner may not accept without issuing a construction change directive.
B. the Contractor may increase the Contract Sum by an appropriate and equitable amount.
C. no change in the Contract Sum is required as the Contractor has volunteered the better quality.
D. if the Owner accepts, removal and correction is not required.
E. if the work was discovered after final payment was made, the Contract Sum cannot be adjusted for this discrepancy.


Answers C. and D. are correct. The Contract Sum can only be reduced by acceptance of nonconforming work, which can be effected post final payment if not previously discovered. Refer to A201-2007 article 12, section 12.3.
are-review.blogspot.com

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Footing cross-section

When the thickness of a foundation wall = 6", the cross-sectional proportions in this image are appropriate for which of the following: A. a footing supported on clay soil B. light frame construction supporting one floor and one roof C. allowable bearing capacity of foundation soil is low in relation to building loads D. when a continuous footing is required Answer B. light frame construction supporting one floor and one roof (in accordance with Table 1805.4.2) ARE 4.0 exam prep: PPP