Skip to main content

Joint checks

A201-2007 under 9.5.3 has a new provision allowing the owner to issue joint checks to the contractor and to any subcontractor contravening an architect withholding certification for payment for the contractor's failure to make payments to the subcontractor.
What is a joint check and why would the owner want to issue this?

AnswerBoth contractor & subcontractor must be present to cash/endorse the check, assuring the claim is satisfied and protecting the project from subcontractors filing liens. This is in the sole option of the owner & the architect will reflect such payment on the next Cert. of Payment.

ARE 4.0 exam study: CDS

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Deflection: steel or wood

For EITHER steel or wood beams, a question that asks for the allowable deflection limit (maximum) for live loads only requires which of the following equations? A. L/240 B. L/360 C. ∆ = 5wl⁴ / 384EI D. ∆ = 5Wl³ / 384EI Answer B. L/360 or span in inches divided by 360. ARE 4.0 exam prep: SS Note on calculations: From posted discussions on AREforum , memorization of most equations is not advised. However, even when the equation may be available in in-exam reference, selection of the appropriate equation requires correct identification.

Facility parking

A new office complex is being planned, which is required to include 162 parking spaces. In addition to the parking spaces, allow for related driveways and walkways to estimate the area of the parking lot that would satisfy this number of spaces. A. 1.0 acres B. 1.5 acres C. 1.75 acres D. 2.0 acres Answer B. 1.5 acres. Multiply the required parking spaces by 400 sf per car (1 acre = 43,560 sf). If walkways are not required, use 300 sf per car. ARE 4.0 exam prep: SPD