How can the Architect be compensated if the Owner continues to use the Architect's Instruments of Service in order to complete the project after the Architect agreement has been terminated (either at the Owner's convenience or by the Architect)?




Answer: By paying a licensing fee to the Architect as compensation as stipulated in 11.9 of the AIA B101 agreement.

For more exam resources also check out these pages CE and PcM-PjM 

Comments

Try These Too!

Building Efficiency

Convert the usable area of classrooms planned with medium efficiency level of new construction to the gross building area given the following model factors: Net Assignable Square Feet: 10,000, Space Factor: 1.5, Building Efficiency Ratio: 67%

Spec coordination

In case there is a discrepancy between specifications and the drawings, which takes precedence? Answer Neither, A201 considers these - quote - complementary and what is required by one shall be binding as if required by all.- unquote. ARE 4.0 exam prep: CDS

Shoring

A slurry wall is a narrow trench filled with a slurry mixture composed of bentonite clay and water, enabling it to resist pressure from the surrounding earth. What type temporary support is this? A. Bracing B. Sheeting C. Underpinning Answer B. It is a type of sheeting. ARE 4.0 exam prep: SPD