During construction, how does the owner unilaterally order changes to the contract without changing its terms?
A by change order document
B by issuing a written order for a minor change
C by construction change directive
D by issuing an addendum
E none of the above



Answer: C. The architect prepares a construction change directive to direct a change in the work prior to an agreement on contract cost and/or time adjustment between the contractor and the owner.

for more ARE5.0 study resources see the CE page

Comments

Try These Too!

Fire detection

Which of the following detector types can detect smoke or a smoldering fire that has not yet burst into flames? A. Ionization B. Rise-of-temperature C. Photoelectric D. Flame detectors

Risk management

How does an owner provide a financial safeguard for the following situations: - unanticipated price escalation of a particular product - an architect’s omission of flashing in the construction documents - a necessary change during construction, modifying the project’s scope. A. Allowance B. Alternates C. Contingency D. Escalation Answer C. Contingency is an amount, usually a percentage, that is part of the project budget to offset changes in the scope of the project, unknown conditions, and gaps/oversights in the documents. ARE 4.0 exam prep: PPP